Edgewood Crossing, East End Marketplace and Eagle Lakes

Project Description

Owner participation agreement (OPA) for the construction of public infrastructure improvements by the participant, with the cost of the reimbursable public improvements (at a rate of 75%) to be reimbursed by the EURA from a portion of the annual net tax revenues generated by the increased value of the property following private development of the site.  Improvements included utilities extensions, street lights, relocating overhead power to underground, storm drainage, curb gutter and sidewalk, landscaping, road improvements, and acquisition costs for right-of-way.

In 2019, the first reimbursement was made to the developer in the amount of $115,336.31.

In 2023, the developer made its second, and final, reimbursement request in the amount of $1,232,663.69, for a total overall reimbursement amount of $1,382,871.58. The board approved the second reimbursement in November 2023.

Public Documents

2023

Reimbursement Request #2 and documentation – November 2023:  https://spaces.hightail.com/space/OWvjHfaJqB

2019

Reimbursement Request #1 and documentation– May 2019: https://spaces.hightail.com/space/PeGaW0bMxK

2018

Pacific West Communities 2014-2017 Property Tax Revenues

2017

Pacific West Communities et al. Agreement to Amend OPA – May 23 2017
Pacific West Communities et al, 2017 Property Tax Calculations

2016

Pacific West Communities et al, Eagle Lakes Reimbursable Public Improvements (Recreational Facilities) LOI – Feb 1 2016
Pacific West Communities et al., Edgewood Crossing, East End Marketplace & Eagle Lakes Reimbursable Public Improvements OPA – Feb 1 2016
Part 1: OPA, Attachments 1-6 
Part 2: Attachment 7 (Part 1)
Part 3: Attachment 7 (Part 2)
Part 4: Attachment 7 (Part 3)
Pacific West Communities et al, 2016 Property Tax Calculations

2014 & 2015

Pacific West Communities et al, 2014 & 2015 Property Tax Calculations